当前位置:城玮文档网 >作文大全 > 旧房改造施工组织设计.(修改后)

旧房改造施工组织设计.(修改后)

时间:2022-08-04 10:40:03 来源:网友投稿

 目录 第一章

  编制说明··············································································1

 第二章

 工程概况···············································································2

 第三章

  指导思想与实施目标························································3

 第四章

  施工准备·············································································4

 第五章

  施工进度计划·····································································6

 第六章

  施工方案·············································································8

 第七章

  质量保证措施···································································33

 第八章

  文明施工··········································································48

 第九章

 安全生产措施···································································51

 第十章

  降低噪音和环境污染措施··············································52

 附表一项目管理机构和人员配备情况·········································61

 附表二拟投入本标段的主要施工设备表······································62

 附表三劳动力计划表······································································63

 附表四施工进度计划横道图·························································64

 ]

 — 欢迎下载 2 第一章

 编制说明 1.1 编制目的: 本施工组织设计是我公司对金洞乡太阳村贫困村户危房改造项目外墙面改造装饰(红色旅游红军街道两边住户房屋风貌改造)工程,本施工组织设计反映了我公司对本工程中选后进行施工管理的总的构思和部署。我们将按照本公司的技术管理程序,在和有关方面进行图纸会审后,按照施工组织设计确定的原则和施工方案进行施工管理,以确保本工程优质高速的建成。

 1.2 编制依据:

 1.2.1、本施工组织设计的编制依据以下文件:

 1.2.2、招标人提供的招标文件; 1.2.3、国家颁布的现行建筑法规、建筑装饰施工的各类规程、规范及验收评定标准; 其主要规范文件是:

 (1)《建筑工程施工质量验收统一标准》GB 50300-2001

 (2)《建筑装饰装修工程施工质量验收规范》GB 50180-2001

 (3)《民用建筑工程室内环境污染控制规范》GB 50325-2001

 (4)《建筑设计防火规范》GBJ16-87(2001 年版)

 (5)《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2001(2002 年局部修订)

 及甘肃省现行有关建筑工程管理的地方性法规、规定; 1.2.4、本公司有关技术管理、质量管理、安全管理、文明施工管理的文件; 1.2.5 本工程施工现场及格周边环境的勘察情况。

 第二章

 工程概况 2.1 工程概况 2.1.1

 工程名称及相关单位 工程名称:

 工程地点:

 建设单位:

 — 欢迎下载 3 2.1.2 工程承包范围 外墙面改造装饰工程设计图纸所示内容为依据。

 2.1.3 工程承包方式:总承包 2.1.4 工期:总工期 45 个日历天 2.1.5 工程质量等级标准,全部工程达到合格标准 2.2 工程特点:本工程施工有利条件 现场施工用地、临时用水、用电均可满足施工要求,这将为工程的按期开工和施工的顺利进行提供可靠保障。工程施工范围相对比较集中,有利于统一控制和管理。施工现场紧邻正式开通的市政道路,物资材料运输和施工机械调运都十分便利,这些都是施工顺利进行的有利条件。本工程施工组织设计重点做好以下工作:

 (1)施工进度计划的安排,在尊重业主方意见的前提下,组织合理的施工场地过渡。严格执行进度计划的安排和调度,处理好甲乙双方的关系。

 (2)制订有针对性的成品、半成品的保护制度,有效地保证已完成产品的质量。

 (3)根据进度计划的安排,制订本工程专项安全生产防护措施,以杜绝在施工期间生产人员和办公人员安全事故的发生,并防止生产人员影响业主的正常务工作。项目部各职能部门和各作业队应严格按照本施工组织设计规定的作业要求进行工作,不允许有违章操作和乱指挥现象的发生。

 第三章

 指导思想与实施目标 3.1 指导思想 本公司将选配高素质有资历的项目经理和工程技术管理人员组成本工程项目部,按照 ISO9001 系列质量标准实施项目工程管理;建立工程质量保证体系,

 — 欢迎下载 4 编制质量计划;积极推广新技术、新工艺、新材料;严格按照施工图纸和验收规范的要求优质高速地组织施工,向业主提供放心满意的产品。

 3.2 实施目标 工程质量目标:合格工程标准工期目标:遵照比选文件中规定的工期日历天数,我公司将在 45 个日历天内完成合同中所述全部工作量。文明施工管理目标:施工现场做到物流交通组织有序,场容整洁,文明施工,达到文明施工现场。

 项目管理目标:对施工的全过程中与质量有关的全部职能活动进 行管理和控制;对特殊、关键部位和过程设置质量控制点,消除不合格品,确保质量目标的实现。采用先进的施工工艺、技术、材料以及机具设备,对施工进度安排、人员配备及格材料的供应实施动态管理,充分保证施工进度和成本目标的实现。

 安全生产目标:

 针对施工现场的具体条件,制订相应的安全生产措施和管理条例,确保安全控制指标的实现,达到安全生产现场。

 第四章

  施工准备 4.1、技术准备 项目部技术人员在前期应进行以下工作:

 4.1.1、编制实施性施工组织设计 施工前项目经理组织技术人员及施工人员进行现场勘察,认真审阅施工图纸, 做好图纸会审与设计交底工作,编制切实可行的施工组织设计,并对所有施工人员进行入场教育,对所有施工人员作好技术交底。

 4.1.2、组织学习图纸及施工技术规范。

 4.1.3、根据建设单位技术人员提供的各楼层水准标高点和网柱轴线定位线,测定本工程施工所用各种定位尺寸,并编制详尽的图文资料。

 4.1.4、做好各类原材料的检测工作。

 4.1.5、做好前期各类工序的逐级技术交底工作。

 — 欢迎下载 5 4.2、材料准备:根据工程所需材料的种类,公司严格按本比选要求的材料品牌购货。各类工程用料及各类施工用材,按计划落实,根据进度需要量分期分批组织进场,有序地堆放在指定的地点。

 4.3、机具准备:按机具准备计划及工程进度的需要,将各类施工机具组织进场并在。机具准备计划详见主要施工机具选择及进场计划)。

 4.4、劳动力准备 根据本工程的特点,公司先行对各专业作业队进行筛选审查,确定后进行培训和技术交底。按施工进度计划和各工种工序的特点分别组织进场作业。

 4.5、在有关人员进场、设备到位、材料试验、测量复核等各项准备工作均完成的情况下,编制开工报告,向监理工程师申请正式开工。

 4.6、阶段施工计划:在各阶段性工程开始前 7 天内,项目部根据该阶段工程的工作内容和特点编制阶段施工计划,并提交给驻地监理工程师及建设单位审批。

 阶段施工计划包括:

 (1)进度计划 (2)施工方案 (3)劳动力安排和设备使用计划 (4)材料采购计划 (5)要求业主的付款计划 (6)请求业主配合的相关工作及要求。

 第五章

 施工进度计划 第一节

  计划安排的原则 1、本项目工程在管理上以计划管理为龙头,认真抓好工程的质量管理和成本管理工作,按业主要求的工期编制好总进度计划及资源计划,并以此确定各个时期的进度目标。

 2、项目部按总计划编制月、旬、周、日作业计划,提前作好人员、材料、机具、技术管理、施工作业面等方面的施工准备工作,确保施工进度的需要。

 — 欢迎下载 6 3、按计划科学、合理的组织施工,实现均衡性生产,不断提高施工技术水平,确保工程质量和工期,改善劳动组织,提高劳动生产率,节约原材料,降低工程成本,实现安全生产,文明施工和创优夺杯的目标。

 第二节

  施工总计划 本工程按招标文件要求日历工期为 45 天,本方案按此工期进行布臵。施工总计划见附图(施工进度计划横道图)。

 第三节

  测量仪器、实验设备需用计划 1、实验检测设备:主要检测试验送由成都市武侯区质检站负责完成,施工现场只准备常用实验工具。

 2、测量仪器从公司本部调入。

 3、拟配备本标段的试验和检测仪器设备表详见附表。

 第四节

 材料供应 砂浆采用现场制作。砂、PK 砖、氟碳漆等材料就地按市场价购买。所需数量随工程进度需要分批调入。

 第五节

 劳动力投入计划 根据本工程的实际情况和工程量的大小,以及机械使用情况,我司拟按附表进行劳动力的计划使用,以避免劳动力的闲臵和发生窝工现象,从而减少人工费的开支。

 详见附表:

 《劳动力计划表》 第六章

 施工方案 6.1、桁、枋、板 1.桁(檩)的制作方法:首先按柱的制作程序画线弹线、去荒、刨光、找圆后,用分杖杆点出中至中的长度,然后依迎头十字中线在桁(檩)上下皮按桁(檩)径的 3/10 均分出金盘线宽度,弹上顺身金线,信线刮出上下两个平面,复弹上顺身中线。桁身四面中线弹上之后,在桁一端,画上榫,另一端画上卯口。按习惯作法:座北朝南的房屋,榫应做在冲东方向的一端,卯应做在冲西方向一端。也就是习惯上的“冲东不冲西”,“晒公不晒母”。而座西朝东的房屋,则应“冲南不冲北”了。榫均做成银锭榫,榫的长度均为桁径的 3/10。两端除做

 — 欢迎下载 7 样卯外,还要按桁(檩)径的 1/4 进行刻半,即匠师们俗称的“二盘檩”。刻半做法是:第一步画出刻半线。依迎头十字中线的横线向桁(檩)顺身返点画刻半长 度,再用角尺对准左右顺身中线,勾画出刻半线,然后用锯锯掉刻半部分。第二步,将盘完头刻半后的桁支起摆正,按规矩尺寸画出两端银锭榫卯,再用锯凿剔榫和卯口。

 2.枋的制作方法:

 1)将打截好的木料架起支稳后,在两端迎头截面上分中,用墨斗吊正找直画出中线,标出枋厚、枋宽的实际尺寸,用角尺依中竖线画出枋的四边线,依四方的四角顶点为准在枋身引出楞线。

 2)将楞线外部分砍削去荒、刨光。在上下皮弹上顺身中线,用分杖杆点出小额枋中的位臵,用掐退的方法画出直榫或银锭榫。

 3)沿榫宽线开锯至断肩线,抬锯,断肩。然后依“掐退”得来的尺寸,做出“肩膀”。肩膀有回肩、抱肩两种。额枋做完榫之后,在断肩处截面上抹去楞角,倒成一个小圆面,称为“回肩”。如果在断肩处的截面上按柱径围大小,向枋身挖出弧面,再抹去楞角倒圆,称为“抱肩”。枋的榫及肩膀做完之后,在枋顺身四角弹顺身线,倒楞,最后只留上下面的顺身中线外,四面用刨净光,编上号。制作工序全部结束。

 3.板的制作方法:

 1)首先按板实际尺寸做出样板(可用较薄的木板),画时应将板与板之间的搭茬处用角尺找方锯出直角,以举架的各架坡度定长,再将各板头尾刮齐。

 随各椽长的样板依次连在一起,根据举折勾画博缝板的曲线,并在随出檐椽长的博缝板下端画出霸王拳形状,经校对无误即可锯出样板。

 2)按样板在已加工好的博缝板料上勾画,画完后依搭茬中线为据,在中线以外画出搭茬分位。最后在博缝板里面点画各桁头位臵中点,以桁径为直径画圆,然后凿剔出深约半椽的桁窝。

 3)沿曲线开锯,用刨净光。挖锯出霸王拳,做出搭茬分位,编号。在安装博缝扳时,应在桁头位臵钉上五星钉或七星钉。

 6.2、木立架和翼角安装

 — 欢迎下载 8 所谓木立架,就是将制作好的大木构件在房屋基址上竖立组装起来。翼角安装,也就是将角梁、翼角椽、翘飞椽等翼角构件组装起来。这些工作都是在构件加工完毕之后,而且经过试组装可行之后才能进行。

 (一)木立架 1.立架前需进行的准备工作:木立架前的准备工作包括核对地盘尺寸,检查柱顶石中至中距离及高低,查对大木构件的数量是否齐备,检查构件榫卯制作是否完全合乎要求;搭建起重架;准备绳索、棍等工具;人员分工以及交待安全 事项等等。这些都是十分必要的,必须认真进行。

 2.大式大木立架:大式大木立架是在搭好起重架、人员分工明确、安全措施制定等各项准备就绪之后才能开始。立架应先立大木柱子,在立柱之前,按照编号,将各柱搬运到各自位臵。然后先从明间开始,先立钻金柱,再立前、后金柱,前、后檐柱,依此次序向明间两边延伸,最后立角檐柱、金柱及两山面的排山柱。如不带钻金柱的建筑物,则先立前后金柱。柱子立起后,为防止晃动,可用绳系在起重架上,临时固定。柱子立完后,用撬棍在柱角卯口拨动进行校正,并先将金柱与檐柱之间的穿插枋安装入位。接着小额枋、由额垫板、大额枋吊上,插入柱头卯口。安装好后,对柱子进行“草拨”拨正,使檐柱在装好柱头构件后不会有大的歪闪。“草拨”之后,将七架梁(或五架梁)的随梁枋吊上插入前后金柱的卯口中,再将金柱头的金枋、金垫板吊运上来安装就位,然后用撬杠、推磨等工具从明间开始,按外檐柱、前金柱、后檐柱、后金柱、两山面檐术、金柱、角檐柱的顺进行拨正。拨正之后,用一根长至柱头的尺杆将线挑起,在线的下端拴上墨斗或线坠。吊檐柱时以升线为准,尺杆上端中点对准柱身中线与升线上端的交汇点进行吊正。吊金柱时也是这样,以柱身中线为准进行吊正,吊线操作时一定要站直看正,切忌马虎草率。柱子拨正后,随手打上大木戗,进深打迎门戗,面阔打龙门戗,两种柱的上端均与枋子绑在一起,在柱根部位打上撞扳并用泥封上。在整个立架过程中,要经常检查这一部位,以免影响立架质量。大木柱的木戗打完以后,柱脚与柱顶石之间可能会出现微小缝隙,可用厚度合适的竹片或铁片塞楔,以保证柱子稳定,拨正后的柱子应当行行成直线,不能有歪闪现象。拨正完成之后,在前后檐外拴搭落檐架

 — 欢迎下载 9 子,架子高低为小额枋下皮跨下 16~32 厘米,,距檐出约 192 厘米。总之以安装斗和钉椽铺望操作方便为目的。架搭好即可着手安装斗。

 安装梁架之前,要先在架子绑好称。吊称的数目要根据所吊起的重量而定。一般情况下,每杆大木称的吊载重量为 250 千克,如梁的份量为 700 千克,就需要 3 杆称同时吊起。每吊装完一层,绑一次称,各梁架全部安装完后,进行一次梁架拨正。梁架拨正正要以中线为准,如瓜柱两侧的柱身中线要对准梁的顺身中线等等。然后用吊称吊装各桁。安装桁从脊桁开始,依次往下安装。注意:同一层举架的桁,一定要对齐桁与桁上皮的顺身中线,桁与桁搭交后成一条顺直线。各桁安装完毕,大木立架即告完成,接着进行翼角安装和钉椽铺望。

 (二)翼角安装庑殿、歇山层顶转角有顺梁法、扒梁法、抹角梁法和迭梁法四种。翼角安装分为角梁安装、翼角椽安装、翘飞安装及铺钉望板等程序。

 1.角梁安装角梁安装是与大木安装同时进行的。角梁安装总的要求是位臵准确,高低进出一致。要达到这些要求,安装时必须做到中线与中线相对,即所谓“黑对黑”。角梁侧面的老中、里外由中要与搭交檩脊面中线相对,各中线相对,就基本保证了角梁平面位臵的准确性,同时还要保证角梁梁头标高的一致性。安装角梁的另一个要点是切记要安角梁钉(制作角梁时已有暗销的要栽上暗销),使老角染和仔角梁成为一体。在实际工作中,有用钻将老、仔角梁钻孔以螺栓连接,此法比用角梁钉或暗销更牢固可靠。

 2.翼角椽安装(以圆椽为例)翼角椽安装主要包括以下程序:分点翼角椽尾部椽花、小连檐、分点翼角椽头部椽花,安装枕头木、钉翼角椽、牢檐、截椽头等。后要保证空气流通(注:屋面板表面的聚乙烯薄膜保护层,若经长期日晒雨淋后,会使安装完成后难以揭去)。

 (1)分点翼角椽尾部椽花。在角梁两侧由椽槽后边缘线开始,以 0.8 椽径(六方建筑用 0.5 椽径,入方建筑用 0.4 椽径)为一格向前分点,有几根翼角椽分点几格,并盗卖翼角椽列次序标上 1、2、3、4……… (2)小连檐。小连檐是联结檐椽椽头的构件,在正身部位,小连檐是直的,到翼角部位,由于角梁的冲出和翘起,使小连檐成为既向上翘起,又向前冲出的双向变曲构件,在安装时必须用麻绳棍缮,使之弯曲成形,在翼角安装中,小

 — 欢迎下载 10 连檐是一道关键性工序,连檐得合适与否,对整个翼角的安装质量及造型有直接影响。连檐的程序是:先将连檐近角梁一端截成 45 度斜头,塞入预先剔好的小连檐口子内用钉子钉住。在与翼角椽相邻的正身椽椽头向后退一雀台别上一支钉子,以挡住连檐另一端不至于向下滑动。然后,在连檐中段拴上麻绳,将绳另一端绑在斗或其他固定木件上,拴好绳后,即可插入棍打,将连檐票弯,此时,需观测连檐弯曲程度,应当弯曲自然缓和,不通报有死弯,整个建筑物各角连檐的曲度应当一致。

 (3)分点翼角椽头椽花(椽子位臵线)。票好小连檐以后,在连檐上分点翼角椽头部分的椽花,方法是:随连檐曲线量出紧邻最末一根翼角椽的正身檐椽中至梁头侧面这一部分连檐的长,再加 0.7 椽径,用这个长度除以翼角根数加1,所得之数即为相邻两根翼角椽中至中的距离,然后从角梁侧面沿连檐量一长度点一点,这点就是第一根翼角椽的椽头部分椽花。确定了翼角椽头尾的位臵,即可按根对位安装翼角椽。

 (4)安装枕头木。枕头木是垫在檐檩与翼角檐椽这间的一块三角形木头。其作用是支撑翼角椽头部翘起,枕头木长同檐步架,厚 1 椽径,与檐檀金盘迭交,并钉在檐檩上,上面承托着翼角椽。因翼角椽沿小连檐的走向渐次改变方向和高度,所以,枕头木的上面呈一个同小连檐曲线平行、相似的弧形。为卡住每根翼角椽,还需在上面挖出椽碗。

 (5)钉翼角椽.钉翼角椽须从第一根开始钉起。将制作好的第一根翼角椽后尾贴入椽槽,使其靠正侧的外皮对准第一格与第二格之间的椽花线,尾部入位 后,先看檐头的中是否与连檐上的椽花线相对,如果相对,说明翼角椽肥瘦合适,如果头偏向角梁一侧,说明偏瘦。解决的办法是将椽子向后撺,直至合适为止,然后再按后尾椽花位臵将撺进去的部分截去,并将后尾肥瘦修理合适。若椽头偏向另一侧,则说明椽子腰部偏肥,需将两肋部分砍削下适当厚度,以使椽头对准连檐椽花点。与此同时,还要看枕头木的高低是否合适,如果枕头木高,可用扁铲剔修,使椽碗高低合适,翼角椽钉在角梁上,每根椽钉不少于3 根钉,在尾子部分的前、中、后各钉 1 颗钉子。钉子不能钉在一条线上,以免将椽钉劈,钉牢之后安第二根翼角椽。第二根翼角椽。第二根翼角椽靠正身的外皮要贴在第二与第三格格间的椽花线上,以后各根按第一根安装程序安

 — 欢迎下载 11 装。安装翼角的关键有三个方面,一是翼角椽的肥瘦要合适,保证每根椽头、尾部都与椽花线相对。在安装中如果有一根椽有偏差,尚可补救,若有大的差错,必须拆掉重钉。二是枕头木及椽碗的高低一定要修整合适,要保证椽尾顺当装入椽槽,中间与枕头木椽碗伏实,头部正好与小连檐贴紧,既不能低于小连檐,也不能挑着小哝檐,只有这样,才能保障小哝檐固有曲线不变。三是尾部要钉牢。翼角椽的第一根直接钉在角梁上,第二根钉子要钉透第一根、并与第一根穿牢,如同穿竹排一样,所以钉翼角椽尾部钉子又叫“穿排子”,只有钉结实,排子穿牢固才能保证翼角的工程质量。

 (6)牢檐、盘截椽头、钉椽头望板,最后根翼角椽钉好之后,将椽子中腰部与枕头木钉牢,将椽头与小连檐钉牢,这道工序中“牢檐”。翼角椽、小连檐、桁檩就连为一体。解去绳,将参差不齐的椽头截齐。翼角钉好以后,需要钉上闸挡板,称为“堵燕窝”。

 3、翘飞椽安装 翼角椽及椽头望板安装完毕,正身飞椽钉上以后,开始票大连檐、氏翘飞。大连檐宽 1.2 椽径,高 1 椽径,上口留有 1/3 椽径宽的平面,断面呈直角梯形,是联系飞檐椽头的构件。翼角部分的大连檐要随冲、翘票成曲线,由于大连檐断面大,不易票,所以制作大连檐时,在起翘部分水平拉出 3-4 道锯口,把整连檐锯口用手锯不宜用电锯,以免锯口过宽影响连檐高度。大连檐制作好之后,应及时浸入水中,以便安装时具有韧性。钉翘飞椽也是从第一根开始钉起, 先将翘飞椽放在对应位臵,按尾部椽花线,把尾部肥出的部分砍去,跟线以后,即可加钉,钉时注意使翘飞母的楞线与小哝檐外皮对齐。先用小钉钉尾子,使之固定,再将翘飞头与大连檐用钉钉住,位臵相对固定后,看一下是否还有手病需要整理,然后再加钉钉牢。翘飞钉完之后,在各飞椽之间要安闸挡板,以防鸟雀入内作巢。可以在翘飞母处刻槽将闸挡板嵌入槽内,也可在各翘飞档内塞上菱形木块,用钉子钉住。但一定要塞严、平齐,不能露脏。这一切工作完成后,将翘檐头望板铺钉齐全,整个翼角就安装完毕了。

 6.3、木装修 6.3.1 格扇的制作

 — 欢迎下载 12 (1)格扇的操作工艺顺序刨料、画线、制作、拼装。

 (2)格扇的操作工艺要点 1)刨料:刨料时先确定格扇的边梃断面尺寸。隔心的仔边看现宽为 2/3 边梃看面,进深则为 7/10 边梃进深;隔心的棍条看面宽为 4/5 仔边看面,进深 9/10 仔边进深。绦环板的高为 1/5 格扇宽,裙板的高为 4/5 格扇宽。各部的长度应根据格扇的设计高度和面宽来确定。隔心棂条的长度还应由其的花格形式来确 定。

 2)画线边框:格扇的自身宽度尺寸应根据柱间框槛尺寸,而且确定了每间安装格扇的数量之后才能肯定。

 3)制作:格扇的边梃、抹头、仔屉、花格棂条的线画好,经校核无误后,便可进行锯割、凿眼、断肩、打槽、修正等工作。

 4)拼装:一般应先将隔心拼好,然后进行曲做头缝榫或销子榫。最后将抹头和绦环板、裙板一起来用上起下落法拼装。

 6.3.2、挂落 2、挂落的制作 (1)挂落的操作工艺顺序:刨料、画线、制作、拼装、安装。

 (2)挂落的操作工艺要点 1)刨料:挂落边框断面为小面为看面,大面为进深。由于挂落的花格是依柱间开间的大小,以基本式样反复变化相连,所以断料长度应按设计图样放足尺大样后确定。花牙子的进深同棂条,面宽及高度按设计图样。

 2)画线 1-边框:边框两上交角采用单榫双肩大割角,两旁框下端作钩夹形,画以如意。上框作榫,旁框作卯眼。

 2-花格:花格的棂条画线应按具体式样而定,同格扇。一般说来,丁字相交,采用半榫;十字相交,采用十字刻半榫;斜相交,按图形角度斜半榫;单直角相交,采用大割角,半榫。

 3-花牙子常见的花纹图案有草龙、番草、松、竹、梅、牡丹等,应依设计图样画线。

 3)制作:花棂条及边框制作要求同格扇,花牙子通常做成双面透雕。

 — 欢迎下载 13 4)拼装:一般应从中间向两旁涂粘胶拼,后再装上花牙子。花格拼成后再三边拼上边框。拼装完成后应校核外皮尺寸,并修正花格棂条与花牙子等交接处,打磨光滑。

 5)安装:安装时,先将挂落试安于柱间枋子下,如挂落与柱子、枋子交接处有需要修正的部位,可用铅笔记上,并确定竹销固定的位臵。然后取下挂落,用刨略作修正,在竹销处钻孔,最后将挂落安上,在柱子上钻孔,用竹销将挂落与柱子连接。

 6.4、屋面工程 青瓦屋顶一般采取“撞肩做法“,即先调脊后瓦瓦的做法,施工程序亦可分为苫背、分中号陇、调脊、瓦瓦等。

 6.4.1、苫背白灰渣子泥(碎麦秸或稻草)苫背。

 6.4.2、分中号陇 1、分中。在檐头找出整个房屋的横向中点并做出标记,屋顶中间一趟底瓦中心线应与之重合。然后从两山博缝外往里返两个瓦口的宽度并做出标记。

 2、排瓦档。将木工预先做好的瓦口一个个锯开,退进 15%椽径钉到连檐上。

 3、号陇。将各陇盖瓦的中点平移到屋檐扎肩灰背上,并做出标记。

 4、瓦边垄。在每坡两端边陇位臵拴线、铺灰,各瓦两趟底瓦一趟盖瓦。

 6.4.3、调脊 1、按扎肩灰上号好的盖瓦中,在每坡各陇底瓦位臵各放一块“续折腰瓦”和两块底瓦。下面的一块梯子瓦的下面再放一块凸面朝上横放的底瓦。沿前后坡扯一道横线,该横线沿 3 块瓦底中间通过,高度应比博缝上皮高一底瓦厚。通过调整枕头瓦,使每陇瓦高低一致。

 2、将横线移至脊中开始“抱头”。

 3、扯线铺灰,在脊上正折腰瓦之间瓦盖瓦“正罗锅”。

 6.4.4、瓦 (1)冲陇。扯线铺灰,先将中间的三趟底瓦和两趟盖瓦瓦好。

 (2)瓦檐头。扯线铺灰,将檐头滴子瓦和圆眼勾头瓦瓦好。

 (3)瓦底瓦。先在齐头线、愣线和檐线上各拴一根短铅丝,叫“吊鱼”,它的长度根据线到边陇底瓦翅的距离确定,然后开线。

 — 欢迎下载 14 (4)瓦盖瓦。按楞线到边陇盖瓦陇为准,将和好的盖瓦灰摊放到蚰蜒当上,从下而上依次安放盖瓦。

 (5)捉节夹陇。将摆好的瓦陇清扫干,用小麻刀灰勾抹筒瓦相接处,此工序为“捉节”。四].古建筑彩画 6.5、彩画 6.5.1、起谱子起谱子,就是根据设计在与彩画构件长宽相等的配纸上打画稿。方法是:先量出彩画构件各部位长度和宽度,再裁出相应长宽的牛皮纸(构件长的 1/2 亦可),按明间、次间、梢间依次配齐。然后在配纸上画出 5 大线和所要的画稿(打画稿时均以明间大额枋为准,其余挑檐桁、下额枋均依据大额枋 5 大线尺寸,上下箍头线必须在一个垂直线上)。稿子完好之后,用针按线条图案扎孔。孔要扎透,孔距要均匀(一般 2 毫米孔距),一个殿堂打一个角的画稿即可. 6.5.2、磨生油、过水布、分中、打谱子先在彩画的构件表面抹一层生油,待生油干后,用细砂纸细细打磨光滑,再用湿布揩去粉尘,擦抹干净;找出彩画构件的横中和竖中,标记清楚;将谱子中线与构件中线对齐后抿摊平展,用粉袋循谱子拍打,使构件一清楚显出花纹、线条粉迹。谱子打好之后,凡是用金处需用小刷蘸红土子将花纹描绘出来。

 6.5.3、沥粉 具体操作方法步骤,准备好沥粉尺棍,先从上向下沥箍头,后从左至右沥枋心。再沥岔口线、皮条线。上部的线上搭尺,下部的线和平线要下搭尺。如遇三裹柁,先沥仰头岔口线和皮条线。由合楞分沥,显眼处先沥横线,后沥斜线,然后再沥盒子线。

 6.5.4、刷色 清式各类彩画,无论贴金与否,均以青(群青)、绿、红及少量的香色(土黄色)和此色为主,互相调换。尤其青绿两色运用,向来有固定规则。一是,同一构件相邻部分,青绿两色相间。如箍头为青色则皮条线的外晕为绿,里晕为青色,绿岔口、青楞线绿枋心。箍头必须与楞线的颜色一致。二是,同一间内上、下相邻的构件,青绿两色相错。如明间大额枋是绿箍头、青枋心,则檐檩和小额枋是青箍头、绿枋心。三是,同座建筑相邻两间,青绿两色调换。如明

 — 欢迎下载 15 间大额枋是绿箍头、青枋心,则次间大额枋应为青箍头、绿枋心。檐檩和小额枋就是绿箍头、青枋心。四是,一座建筑物的外檐明间桁条,固定为青箍头。由额垫板的箍头设色同挑檐桁(小式垫板箍头设色亦同檐檩)。柱头箍头为上青下绿。五是,由额垫板与平板枋,如不分段划分部位通刷一色,由额垫板刷 红色,平板枋为蓝色。斗拱刷色以角科、柱头科为准,必须“绿翘绿昂青升斗”, 再向里推,为“青翘青昂绿升斗”,青调换。如遇双数时,中间两攒可刷同一颜色,座斗枋底面一律为绿色。刷色的顺序是,先上后下,先里后外,先小处后大面。每刷完一个色后要认真检查,不能刷错,将色刷得无绺无节,均匀一致。

 彩画使用色彩较多,拍好的谱子有些地方面积较小,写不下颜色名称,为清楚标明各部位使用色侑,古匠师用代号注在彩画用色部位,例如:六代表洋绿,七代表佛青,八代表石黄,九代表紫色,十代表烟子,三代表香色,丹字代表樟丹,白字代表粉,工字代表银朱等等,如果是二绿、三绿色,用二六、三六代替;二青三青用二七、三七代替,这些代号一直沿用至今。

 6.5.5、包黄胶 单粉条和双粉条多数要贴金箔,为了衬托金箔光亮, 在贴金箔前要包一道黄胶。黄胶是用石黄、胶水和适量的水调制而成的(也可用光油、石黄、铅粉调制成“包油胶”)。先包大 6.5.6、拉晕色、拉大粉 将浅青浅绿(三青三绿)刷于金线两侧,由浅至深,这道工序叫“晕色”。箍头晕色宽度一般为箍头宽度的 1/3,其余部位酌情而定。靠金线画一道白线,称为“拉大粉”,后包小粉,将粉条包满。无论黄胶或包油胶,胶量不宜过小,以免金胶油浸透而推动作用。靠金线画一道白线,称为“拉大粉”,粗细以晕色 1/3为度。这条白线还可以起到齐金作用。拉晕色时要用尺棍,用小刷按晕色的位臵、宽窄适当拉好,曲线部位按曲线拉。最后用刷子将晕色拉匀。凡有晕色之处,靠金线必须拉大粉,做法与晕色相同。较细的白粉道,是顺着草花纹样的三色外缘,画一道细的线,叫做“行粉”。

 6.5.7、压老

 — 欢迎下载 16 一切颜色都描刷完毕之后,用较深的颜色,如黑烟子、砂绿、佛绿、深紫、深香色等,在各色的最深处一边,用画笔润一下,以使花纹突出,这道工序叫“压老”。在死箍头正中划一道黑线,名为“掏”。檩头、柱头刷黑,称为“老箍头”。

 攒活最后一道的深色,名为“攒老”,如硝红底攒银朱,深紫压老;石黄底攒香色,深香色压老;三绿底攒砂绿,深砂绿压老。

 6.5.8、打点找补 彩画结束之后,详细检查,将遗漏、滴洒胜脏处用原色补齐,由上而下清理干净。这道工序必须仔细认真,不能图省事。打点找补结束,彩画才算真正完工。

 6.6、古建油漆 古建油饰工程可分为三大工序。即清理底层、地杖、刷饰。

 6.6.1、清理底层 (一)斩砍。斩砍是古建油饰清理底层的代表项目。旧建筑油饰的砍活称之砍旧活,是去掉木色表面上的旧有油饰。旧油饰的做法及破损情况很不一致。造成不一致的因素很多,所以砍旧活的要求比砍新活的要求复杂得多。在砍旧活时,只用一种方式是达不到清理目的的,必须结合挠、铲、撕、剔一起进行,所以有砍净挠白、撕、剔一起进行,所以有砍净挠白、撕全剔到之说,这就是对砍旧活的具体要求。

 (二)挠、洗、烧 挠活主要是修缮旧活中清理底层的一种方式,因为挠活不只是辅助砍活的挠灰底疤。挠活是针对不需要斩砍或无法斩砍的纤细部位或花活部位,直接以挠的方式进行清理的独立工序。这些部位绝大多数是属于木构的装饰物,所以对挠活的操作要求要比斩砍细致得多,也较为重要。

 (三)除铲 除铲是清理底层的又一种方式,俗称刮铲打扫。其应用比较广泛,无论是营建新活还是修缮旧活,都是必不可少的工序。但凡古建的木作部分。包括木结构、木基层、木装修,其露明的木表面,都要进行油饰或彩画。营建新活凡是不需要剁斧迹的部位、修缮旧活凡是不需要去掉旧饰面的部位,在做地杖或腻子前,

 — 欢迎下载 17 都必须进行彻底的刮铲打扫,方可进行下一道工序。

 (四)撕缝 撕缝是在油作清理底层中一道附加工序,在砍、挠、铲的清理中,都是必不可少的。只要是木构建筑,缝子是很难避免的,构造缝和木材表面的自然裂缝都属需撕之列。

 所谓“撕缝,就是把原有缝隙的口部再开大一些,目的是在做地杖时,能使地杖灰较容易的进入缝隙之内。撕缝的要求:

 ①用油工专用铲刀,把缝口两边的直角铲成八字楞的破口,使缝隙口形成长形漏斗状,以便做地杖时使掖灰或捉腻子容易挤至缝隙的深部。

 ②遇缝隙无论是构造缝或自然劈裂缝,均作撕缝处理。大缝大撕,坡口宽度应是原缝口宽度的两倍。

 ③遇缝内嵌有木条时,应视木条两边为两道缝,分别做撕缝处理。不仅缝口边要铲成八字坡楞,木条的边愣也要铲成八字。

 ④铲完缝口坡楞,还应把刀尖插入缝内,随缝隙走向来回划动几次,使缝隙内两面三刀侧之木面见了新茬,以便做地杖时,能吸收灰内的油质。

 ⑤修缮旧活时,缝隙中一般都嵌有木条或地杖灰,凡是活动了的都必须剔出来, 只有在缝内结合牢回不动的可以不剔出。对剔开的缝隙也要用刀尖庄缝内划动几次,并用硬毛刷子把缝隙内的积尘、木屑、灰颗粒等清扫干净。

 (五)剔、刻、刮 在修缮旧活时遇到雕刻花活,如牌楼上的云龙透雕花板、九龙立额的匾边,神龛的透雕蟠龙柱、毗轳帽,菱花隔扇上的浮雕龙凤樘等,要清除其上之旧地杖,采取易、刻、刮的清理方式。

 (六)磨活 磨活在清理底层中,主要针对做清色透木纹饰面的部位,多为室内装修。

 (七)嵌缝子、下竹钉 嵌缝子、下竹钉是清理底层工序中对木表面缺陷的处理措施。在撕缝一节中已详述了对缝隙的处理方法。不过,撕缝只是小窄缝隙的处理措施,对于宽、大、深的缝子,就应用木条嵌入缝内,使一道大缝变成并行两道小窄缝,然后

 — 欢迎下载 18 进行撕缝。在营建新活或修缮旧活的清理底层工序中,都必不可少的。下竹钉则只是对营建新活的大木部分嵌自然劈裂缝则的附加措施。对大木的构造缝及木基层和木装修的缝子,无论大小都不需要下竹钉。在修缮旧活时,对大木的自然劈裂缝,因多年的风干,涨缩的变化已极微,故没有必要再下竹钉了。下竹钉是油漆传统作法,今多省略,以木条代之。

 (八)汁浆 木料虽经砍挠打扫,但缝内尘土很难清静,故汁油浆一道,以 1 油满:1 血料:20 水调成均匀油浆,不宜过稠,用糊刷将木件全部刷到(缝内也要刷到),使油灰与木件更加衔接牢固。

 6.6.2、地杖 1.捉缝灰 油浆干后,用笤帚将表面打扫干净,以捉缝灰用铁板向缝内捉之(横掖竖划)使缝内油灰饱满,切忌蒙头灰(就是缝内无灰,缝外有灰,叫蒙头灰)如遇铁箍,必须紧箍落实,并将铁锈除净,再分层填灰,不可一次填平。木件有缺陷者,再以铁板衬平借圆,满刮靠骨灰一道。如有缺楞少角者,应照原样衬齐。线中鞅角处须贴齐。干后,用金刚石或缸瓦片磨之,并以铲刀修理整齐、以笤帚扫净,以水布掸之,去其浮灰。

 2.扫荡灰 扫荡灰又名通灰,作在捉缝灰上面,是使麻的基础,须衬平刮直,一人用皮子在前抹砂(名为插灰),一人以板子刮平直圆(名为过板子),另一人以铁板打找捡灰(名为捡灰),干后用金刚石或缸瓦片磨去飞翅及浮籽,再以笤帚打扫,用水布掸净。

 3.使麻 (1)开头浆、用糊刷蘸油满血料(1:1.2)涂于扫荡灰上,其厚度以浸透麻筋为度,不宜过度。

 (2)粘麻:前面开头浆,后面跟着将梳好的麻粘于其上,要横着木纹粘,如遇木件交接处和阴阳角处,随两处木纹不同,也要按缝横粘,麻的厚度要均匀一致。

 — 欢迎下载 19 (3)轧干压:名为轧麻,麻经粘上后,以若干人用麻压子先由鞅角着手,逐次轧实,然后再轧两侧,注意鞅角不得翘起,干后如出现断裂者,名为“崩鞅”。

 (4)潲生:以油满和不(1:1)混合一起调匀、以糊刷涂于寐上,以不露干麻为限,但不宜过厚。

 (5)水压:随着潲生后,再以麻压子尖将麻翻虚(不要全翻),以防内有干麻,翻起后再行轧实,并将余浆轧出,以防干后发生空隙起凸现象。

 (6)整理:水压后再复压一遍,进行详细检查,如有鞅角崩起,棱线浮起或麻筋松动者(名为抽筋),应予修好。

 4.压麻灰 麻干后,以金刚石或缸瓦片磨之,使麻茸浮起(名为断斑),但不得将麻丝磨断。用笤帚打扫,以水布掸净,以皮子将压麻灰涂于麻上,要来回轧实与麻结合,再度复灰,以板子顺麻丝横惟裹衬,在灰上扎出线脚,粗细要匀要直、平。如工程需要作两道麻或一麻一布者,此时可先不扎线,待上压麻灰或压布时再行扎线。

 5.中灰 压麻灰干后以金刚石或缸瓦片磨之,要精心细磨,以笤帚打扫,以水布掸净,以铁板满刮靠骨灰一道,不宜过厚。如有线脚者,再以中灰扎线。

 6.细灰 中灰干后用金刚石或缸瓦片将板迹接头磨平,在笤帚打扫,以水布掸净,再汁水浆一道(净水),用铁板将鞅角、边框、上下围脖、框口、线口、以及不下去皮子的地方,均应详细找齐。干后再以同样材料用铁板、板子、皮子满上细灰一道(平面用铁板,大面用板子,圆者用皮子)、厚度不超过 2 毫米,接头要平整,如有线脚者再以细灰扎线。

 7.磨细钻生 细灰干后,以细金刚石或停泥砖精心细磨至断斑(全部磨去一层皮为断斑)

 ,要求平者要平,直者要直,圆者要圆,以丝头蘸生桐油,跟着磨细灰的后面随磨随钻,同时修理线脚及找补生油(柱子要一次磨完、一次钻完),油必须钻透(所谓钻透者就是浸透细灰),干后呈黑褐色,以防出现“鸡爪纹”现象(表面小龟裂),浮油用麻头擦净、以防“挂甲”(浮油如不擦净,干后有油迹

 — 欢迎下载 20 名为挂甲)。俟全部干透后,用盆片或砂纸精心细磨,不可遗漏,然后打扫干净,至此,一麻五灰操作过程就全部完成了。

 6.6.3、油饰 我国旧式油漆,均以光油为主,其中加入樟丹、银朱、广红等颜料,以丝头蘸油搓于地仗上,再油以拴横蹬竖顺,使油均匀一致,干后光亮饱满,油皮耐久,永不变色。其操作过程如下:

 1.浆灰 以细灰面加血料调成糊状、以铁板满克骨一道,干后以砂纸磨之,以水布掸净。

 2.细腻子 以血料、水、土粉子(3:1:6)调成糊状,以铁板将细腻子满克骨一遍,来回要刮实,并随时清理,以防接头重复,干后以砂纸细磨,以水布掸净。

 3.垫光头道油 以丝头蘸配好的色油,搓于细腻子表面上,再以油拴横蹬竖顺,使油均匀一致,除银朱油先垫光樟丹油外、其他色油均垫光本色油,干后以青粉泌之,以砂纸细磨。

 4.二道油(本色油)操作方法与垫光油同。

 5.三道油(本色油)操作方法与垫光油同。

 6.罩清油(光油)以丝头号蘸光油(不加颜料者)搓于三道油上,并以油拴横蹬竖顺,使油均匀,不流不坠,拴路要直,鞅角要搓到,干后即为成活。

 (3)椽望油漆,老檐应由左而右,飞檐应由右而左操作之。搓绿油时,如手有破伤者不得操作,以防中毒。洋绿有剧毒,宜慎之。

 6.7 墙面涂料工程(氟碳漆)

 1、材料准备:

 根据设计图纸及甲方要求选定涂料及喷涂材料样品,并要求厂家提供合格证、复验报告以及必要的准用证。材料进场组织材料员、技术员、工长、监理人员进行现场验收,合格后方可使用。

 2、施工工艺 2.1、基层要求

 — 欢迎下载 21 (1).氟碳漆对基材要求跟一般外墙漆的要求一样,基材必须结实、耐水、 pH <10 、含水<8% 、无灰、无霉斑等,更高的要求是批灰层必须防水、抗裂、抗碱、结实、平整度《2 mm 、好施工、成本合理、耐用 30 a 以上。

 (2).抹灰和混凝土的基层质量应符合《JGJ 建筑装饰工程施工及验收规范》; (3).抹灰层或混凝土表面层(包括分割缝、窗框周围等)不得有污物; (4).基层表面必须牢固、无酥松,不得有裂缝或起壳,平整度≤2mm,基层无浮尘,无粘附颗粒物; (5).抹灰和混凝土基层涂刷外墙涂料要求含水率不得大于 10%,PH 值不得高于 9,新粉刷水泥砂浆墙面夏季要求养护 10 天以上,冬季需 20 天以上,现浇混凝土墙面夏季需养护 21 天以上,冬季需 28 天以上。

 2.2、基面处理 (1).检查墙面平整度,大的突起处需砂磨平整,大的凹陷或孔洞处用水泥砂浆进行填补并打磨平整; (2).对墙面较大裂纹进行切割,并连续多遍进行填充高弹腻子,直至墙面平整,腻子干燥后打磨平整; (3).用毛刷、铲刀或砂纸清除墙面的颗粒杂物,铲除墙面酥松的水泥层; (4).处理完毕要求符合平整度要求≤2mm; (5).墙面达到基本清洁,无浮尘,无粘附颗粒物。

 2.3、满批氟碳漆专用抗裂腻子 (1).采用氟碳漆专用抗裂腻子:氟碳漆抗裂腻子专用添加剂:水=20;1;8 的比例进行腻子的调配,腻子必须用手电钻进行充分搅拌均匀, (2).最长放置时间为 4 小时,超过 4 小时不得使用,已经固化的浆料也不能使用;检查墙体表面有无颗粒粉尘等沾污物,应该将其清理干净; (3).用两米长的铝合金靠尺拖刮腻子,先竖刮一遍,然后横刮一遍,靠尺运行速度及用力应均衡,否则会沿靠尺运动的方向形成波浪状而影响其平整度; (4).粘贴装饰胶带,按要求进行界格条的分割,界格分好后披腻子,然后逐遍将胶带撕下; (5).腻子一般批嵌 4-5 遍;

 — 欢迎下载 22 (6).腻子层干燥(一般不超过 4 小时)后进行砂磨。时间太长,腻子干硬,将很难砂磨(浪费人力和砂纸),必须将粗糙腻面完全磨光,否则后续施工将浪费大量腻子; (7).应采用 120 目或 150 目砂纸打磨; (8).腻子打磨后墙面凸凹不平现象应彻底消除,同时修直阳角和腰线。

 2.4、抛光腻子施工 (1).在打磨平整的腻子上进行抛光腻子的施工; (2).要求表面无批刮印痕,尤其是阴阳角、滴水线、窗沿及落水管附近墙面; (3).线条平直、阳角笔直,无残缺; (4).用指甲抠无掉粉现象,粘结力合格; (5).手感平滑,无凸凹及起伏的感觉。

 2.5、底漆喷涂 (1).检查腻子是否符合要求,有问题的地方及时修补; (2).在完全干燥的墙面(墙体要干燥,墙面含水率小于 8%)上喷涂底漆(气压在 5-8kg/cm2,无水喷涂); (3).要求喷涂均匀,不能漏喷,颜色应保持均匀一致,不得出现发花现象,刮风(六级以上)及雨天不能施工。

 (4).底漆喷涂一遍,喷涂完毕进行检查,发现墙面有批刮印痕或蜂眼现象,必须打磨至符合要求; (5).打磨应采用 280 目或 360 目水磨砂纸,打磨应仔细,注意不能将涂膜磨穿; (6).打磨完毕应进行除尘处理,用抹布等将墙面上打磨产生的粉尘处 (7).底漆喷涂后,应颜色均匀,光泽均匀,涂膜表面光滑,无粉尘等污渍。

 2.6、氟碳面漆喷涂 (1).底漆必须完全干燥,墙面不得有粉尘等杂物; (2).施工配比,主漆:固化剂:稀释剂=10:1:2; (3).调配后的氟碳漆必须采用 200 目纱网进行过滤,稀释剂在放置过程中应不断搅拌,以免沉淀;

 — 欢迎下载 23 (4).喷枪型号:W-77,喷嘴尺寸:1.5-2.0mm,气泵压力:0.3-0.5Mp; (5).施工时应考虑喷涂人数、喷涂面积、喷涂基面、吊笼分布的配合,考虑到本工程的实际情况,安排施工人员同时进行喷涂,在保证不流挂的前提下,尽可能的喷厚一些; (6).应做好防污和防毒工作,对落水管等应进行保护,工人施工时应戴防毒面罩和手套等防护用品,同时严禁烟火;喷涂应均匀,密度合理,无流挂、明暗不均、发花等现象,手感细腻,光泽均匀,无批刮印痕和凸凹不平现象。

 3、质量要求 3.1 涂料的品种规格、质量、色彩必须符合设计要求。

 3.2 必须与基层粘接牢固。

 3.3 喷涂表面颜色一致,花纹、色点大小均匀,不显接茬,无漏刷、透底和流坠。

 3.4 分隔条宽度一致,平整光滑,棱角整齐,横平竖直,通顺。

 3.5 分格缝平直 5m 拉线检查 3mm。

 4.成品保护 4.1 喷涂前应对窗口进行遮盖,如喷到窗框上应及时清理擦拭干净。

 4.2 拆架子时,要严禁碰撞墙面和污染涂层。

 4.3 油工在施工操作时严禁蹬踩已施工完的部位,防止油漆等污染墙面及塑钢门窗。

 4.4 施工 1~2 小时内避免雨淋,应加强天气预报工作,下雨天不准施工。

 4.5 室内施工时一律不准从窗口往外倾倒垃圾。

 5.安全施工措施 5.1 高空作业必须系好安全带。

 5.2 严格按照吊篮施工要求操作。

 5.3 五级风以上停止作业。

 5.4 严禁高空落物。

 第七章

  质量保证措施 7.1 组织保证措施

 — 欢迎下载 24 本工程项目在组织机构上形成质量保证体系,项目经理对工程质量负总的行政职责,负责对影响工程质量的各要素进行配置,确保以足够的技术人力资源和物质投入到本工程的管理之中。分工负责的岗位制。项目部所有管理人员均是质量保证体系中的有机组成部分,分工负责,对本工程实行全员全过程的质量管理。

 分工如下:

 技术负责人:总管技术质量工作,对技术交底质量检验负直接领导责任; 生产副经理:总管生产计划、劳动力、材料调度、安全生产工作的,对施工进度、工序交接和原材料采购进场负直接领导责任; 施工员:负责所辖工段作业的技术交底、工艺操作的技术管理,对技术工作负直接责任; 质检员:负责所辖工段的工程质量监督、检验的工作,对工程质量负直接责任:

 资料员:负责本工程的技术资料、质量检验资料的收集、整理、保管及交验工作,对资料工作负直接责任:

 综合员:负责本工程承包范围内的全部预算、结算工作,对预结算工作负直接责任; 材料员:负责工程原材料半成品的计划、采购、验收工作,对材料工作负直接责任; 安全员:负责施工过程中人员及现场安全管理工作,同时负责施工过程中成品及半成品的保护,对上述工作负直接责任。

 本项目的质量保证体系见下图:

 7.2 技术质量措施 ...

相关热词搜索: 旧房 施工组织设计 改造